At
9:00 amon 6th Jan 2017, Vietnam Expressway Corporation (VEC) held the opening ceremony of the
technical bid for package no.10 – procurement of O&M equipment (JICA
funded) under the Ho Chi Minh – Long Thanh – DauGiay Expressway Construction
Project.
At
the time of the bid closing, there were three (3) bidders submitting bids
including Vietnam – Japan Technology & Science Equipment Co.,ltd, HiepHoa
Equipment of Environment and Trading Co.,ltd, and VT P.L.U.S Import – Export
Co.,ltd.
The
package was undertaken in the type of national competitiveness with the “one
stage - two envelopes” mode. At the time of bid opening, only technical bids
were publicly opened and after completed technical bid evaluation, only the
financial bid envelope of the technically responsive bidders shall be further
opened.




The
opening ceremony was held publicly with transparency and compliance with the
legal regulations of Viet Nam and JICA.
Previously,
on 21st November 2016, General Director VEC – Dr. Mai Tuan Anh approved the bid
documents of the package No.10 in the Decision no.738/QĐ-VEC).
O&M
is a necessary item for maintaining the quality of the expressway after being
put into operation. Moreover, the O&M equipment shall assist VEC in
actively maintenance and repairingthe damages caused by the natural disasters,
traffic rescue and other damages during operation.